The Saldanha Bay Municipality intends to commence with its resealing and resurfacing programme for the 2026/27 financial year. The project kicks off in Vredenburg on 16 September 2026, followed by the establishment of sites throughout the municipal area, weather permitting.
Vredenburg Projects: 16 September – 16 October 2026
Roads under consideration for this period:
- Tromp Street
- Woltemade Street
- Bester Street
- Smith Street
- Swart Street
- Houtkapper Street
- Kanna Street
- Lupine Street
- Lyster Street
- Jupiter Street
St Helena Bay Projects: 12 October – 30 October 2026
Roads under consideration for this period:
- Ecklonia Street
- Malgaslelie Street
- Sonkwasriet Street
- Rudder Street
- Sandy Bay Drive
- Bella Prima Avenue
- Katonkel Crescent
- Rocket Crescent
- Dolphin Street
Saldanha Projects: 2 November – 27 November 2026
Roads under consideration for this period:
- Biskop Street
- Orion Street
- Sagitta Street
- Noordsee Street
- Pluto Street
- Aries Street
- Perlemoen Street
Hopefield Projects: 12 October – 27 November 2026
Roads under consideration for this period:
- Sonneblom Street
- Tarentaal Street
- Baard Street
Langebaan Projects: 2 November – 11 December 2026
Roads under consideration for this period:
- Benguela Road
- Kompanje Close
- Anker Close
- Skipper Close
- Anchorage Street
- Viooltjie Street
- Katonkel Crescent
- Delos Street
- Naxos Street
- Ascot Street
- Strand Street
- Kotze Street
- Oester Street
Paternoster Project: 26 October – 30 October 2026
Road under consideration for this period:
- Korhaan Street
Motorists are advised to make use of alternative routes, were applicable, to minimise disruption.