The Saldanha Bay Municipality intends to commence with its resealing and resurfacing programme for the 2026/27 financial year. The project kicks off in Vredenburg on 16 September 2026, followed by the establishment of sites throughout the municipal area, weather permitting.

Vredenburg Projects: 16 September – 16 October 2026

Roads under consideration for this period:

  • Tromp Street
  • Woltemade Street
  • Bester Street
  • Smith Street
  • Swart Street
  • Houtkapper Street
  • Kanna Street
  • Lupine Street
  • Lyster Street
  • Jupiter Street

St Helena Bay Projects: 12 October – 30 October 2026

Roads under consideration for this period:

  • Ecklonia Street
  • Malgaslelie Street
  • Sonkwasriet Street
  • Rudder Street
  • Sandy Bay Drive
  • Bella Prima Avenue
  • Katonkel Crescent
  • Rocket Crescent
  • Dolphin Street

Saldanha Projects: 2 November – 27 November 2026

Roads under consideration for this period:

  • Biskop Street
  • Orion Street
  • Sagitta Street
  • Noordsee Street
  • Pluto Street
  • Aries Street
  • Perlemoen Street

Hopefield Projects: 12 October – 27 November 2026

Roads under consideration for this period:

  • Sonneblom Street
  • Tarentaal Street
  • Baard Street

Langebaan Projects: 2 November – 11 December 2026

Roads under consideration for this period:

  • Benguela Road
  • Kompanje Close
  • Anker Close
  • Skipper Close
  • Anchorage Street
  • Viooltjie Street
  • Katonkel Crescent
  • Delos Street
  • Naxos Street
  • Ascot Street
  • Strand Street
  • Kotze Street
  • Oester Street

Paternoster Project: 26 October – 30 October 2026

Road under consideration for this period:

  • Korhaan Street

Motorists are advised to make use of alternative routes, were applicable, to minimise disruption.